Load Shedding


Load shedding is what electric utilities do when there is a huge demand for electricity that exceeds the generation available. The alternative is to have a brown-out where the voltage is reduced. 

It costs a lot to have generators standing by just in case there is a surge of demand, and the operators of those generators expect to be paid whether they run the generators or not. An alternative is if there is a large consumer of electricity (say, a factory) that could suddenly turn off all its electricity demand, they could agree to do that on request, and it has the same benefit as adding that amount of generation to the electric grid. In fact, it's better -- as there is less demand on the wires which are often saturated at the same time. 

That factory has losses from shutting down its equipment and idling its workers, but if the money it gets paid is enough, then it's worth it. This is an example of load shedding. 

There are many other cases where lots of smaller consumers agree to reduce demand on hot summer days, such as by reducing air conditioning or lighting. 

Someone who aggregates all these smaller cases can have the same effect as one big generator and so get the same money, and the operators of the electric grid are happy as it effectively solves the peak demand problem. 

When there is a shortfall in the electricity supply, there can be a need to reduce demand very quickly to an acceptable level, or risk the entire electricity network becoming unstable and shutting down completely. This is known as a “cascade” event, and can end in a total or widespread network shutdown affecting very large areas of a country. Some recent examples include the blackouts in northeast America and Canada in 2003 and across Italy in the same year and in India in 2012.

As the system frequency approaches the normal 60 Hz or 50 Hz ,a frequency relay can be used to automatically begin the restoration of the load that has been shed. The amount of load that can be restored  is determined by  the ability of the system to serve it .The criteria is that   the available generation must  always exceed  the amount  of  load being restored so that the system frequency will continue to recover . Any serious decrease in system frequency at this point could lead to undesirable load shedding repetition, which could start a system oscillation between shedding and restoration. This would be a highly undesirable condition. The availability of generation, either locally or through system interconnections ,   determines whether or not the shed load can be successfully restored.
Therefore, a load restoration program usually incorporates time delay, which is related to the amount of time required to add generation or to close tie- lines during emergency conditions. Also, both the time delay and the restoration frequency set points should be staggered so that all of the load is not   reconnected at the same time.  Reconnecting loads on a distributed basis also minimizes power swings across the system and thereby minimizes the possibility of initiating a new disturbance.

The drop in frequency may endanger generation itself .While a hydro-electric plant is   relatively unaffected by even a  ten percent  reduction in frequency, a thermal generating plant is quite sensitive  to even a five percent reduction.  Power output of a thermal plant depends to a great extent  on  its motor driven auxiliaries such as boiler feed water pumps, coal pulverizing and feeding equipment, and draft fans. As system frequency decreases, the power output to the auxiliaries begins to fall off rapidly which in
turn further reduces the energy input to the turbine generator. The situation thus has a cascading effect with a  loss of frequency leading to a loss of power which can cause the frequency to deteriorate further and the entire plant is soon in serious trouble. An additional major concern is the possible damage to the steam  turbines due  to prolonged operation at reduced frequency during this severe overload
condition .

Load shedding normally happens in two ways:

Automatic Load Shedding

This is a result of concurrent failures of major element(s) in the national grid (e.g.co-incidental generator or key transmission line failures), resulting in protection schemes initiating the automatic isolation of additional parts of the national grid, to protect the entire grid from cascading to a total blackout. Automatic load shedding always occurs on the transmission system level, with the result being large
amounts of electricity and large blocks of customers taken off supply in a very short time. Typical load reduction amounts can be in the order of 1000MW – 2000MW, affecting hundreds of thousands of customers.

Manual (Selective) Load Shedding

This occurs where time is available (typically up to 30mins) to make selective choices on what customers are shed. Selective load shedding often occurs on the distribution system level, and typically requires medium to small amounts of electricity to be “shed” in a short time (rolling blackout). Typical load reduction amounts can be in the order of 50MW – 100MW, affecting tens of thousands of customers at a time. 

In order to minimise the impact on individual customers and share the burden, rotational load shedding (rolling blckout) will occur on the low priority feeders if the load shedding duration extends for several hours. Typically the first group of customers who were shed will be restored after one or two hours, at the expense of the next group of customers to be taken off supply. This can continue until the supply/demand equation is balanced again and load shedding is no longer required.